Restoring access - Belowra Valley bridges
The Belowra community was left isolated after the 2019 New Year’s Eve bushfires destroyed four crucial timber bridges.
Our teams were soon on the scene to assess the damage and arrange temporary crossings.
All four bridges have now been replaced with permanent structures that are more fire and flood resilient. Given the scale of the damage, we relied on financial assistance from the NSW and Federal governments' Natural Disaster Relief and Recovery Arrangements to get the job done.
Belimbla Bridge
The damage: Completely destroyed
Current status: Permanent access restored
The work: We initially established a side track, which was washed away by flood waters. We then created a temporary bridge to maintain access until the bridge was replaced using the InQuik Bridging System.
Pre-fire: The multi-span bridge before the bushfire
January 2020: After the 31 December bushfire
January 2020: A side track was quickly established to a allow temporary access
February 2020: Flood waters swept away the temporary track after heavy rain
March 2020: Progress was underway with the more resilient temporary timber bridge
July 2020: Flood waters wreaked havoc on the road approaching the temporary bridge
April 2021: A drill rig preps the site for the new bridge piles
June 2021: Formwork for new deck shows the height of the new bridge
July 2021: Traffic is directed off the temporary timber bridge and on to the new bridge
October 2021: The finished product
Previous
Next
Pre-fire: The multi-span bridge before the bushfire
January 2020: After the 31 December bushfire
January 2020: A side track was quickly established to a allow temporary access
February 2020: Flood waters swept away the temporary track after heavy rain
March 2020: Progress was underway with the more resilient temporary timber bridge
July 2020: Flood waters wreaked havoc on the road approaching the temporary bridge
April 2021: A drill rig preps the site for the new bridge piles
June 2021: Formwork for new deck shows the height of the new bridge
July 2021: Traffic is directed off the temporary timber bridge and on to the new bridge
October 2021: The finished product
Previous
Next
Belowra Bridge
The damage: Completely destroyed
Current status: Permanent access restored
The work: We created an initial side track (then recreated the track after it was washed away) to maintain access until the bridge was replaced using the InQuik Bridging System.
Pre-fire: The picturesque timber bridge amid the she oak trees
January 2020: A sudden drop where the bridge used to be
January 2020: Little remains of the old timber bridge
March 2020: The temporary fix provides access again
May 2020: The side track sits adjacent to the ruins of the old bridge
July 2020: Flood waters ripped through the temporary side track
July 2020: The temporary crossing is restored after the flood
February 2021: The new bridge structure is in place awaiting a road surface
Previous
Next
Pre-fire: The picturesque timber bridge amid the she oak trees
January 2020: A sudden drop where the bridge used to be
January 2020: Little remains of the old timber bridge
March 2020: The temporary fix provides access again
May 2020: The side track sits adjacent to the ruins of the old bridge
July 2020: Flood waters ripped through the temporary side track
July 2020: The temporary crossing is restored after the flood
February 2021: The new bridge structure is in place awaiting a road surface
Previous
Next
Four Gums Bridge
The damage: Completely destroyed
Current status: Permanent access restored
The work: We established a temporary side track before replacing the bridge with a concrete structure
Pre-fire: The single-span bridge before the bushfire
January 2020: The damage
January 2020: A dirt side track provides access around the bridge
February 2020: The permanent replacement opened the road on 26 February
Previous
Next
Pre-fire: The single-span bridge before the bushfire
January 2020: The damage
January 2020: A dirt side track provides access around the bridge
February 2020: The permanent replacement opened the road on 26 February
Previous
Next
Sitters Ditch Bridge
The damage: Completely destroyed
Current status: Permanent access restored
The work: We established a temporary side track before replacing the bridge with triple cell piped culverts
Pre-fire: The bridge sat in a lush forest
January 2020: The bridge abutment walls no longer exist and little is left of the deck
January 2020: A temporary track winds around the burnt out bridge
May 2020: The temporary side track was washed away by flood waters and later rebuilt
March 2021: Gabion baskets are installed for the water spillway downhill from the bridge
April 2021: The concrete culverts are in place and the new road is being built above
May 2021: The bridge replacement was opened to traffic in early May
The final product: Guardrail lines the road over the new culverts
Previous
Next
Pre-fire: The bridge sat in a lush forest
January 2020: The bridge abutment walls no longer exist and little is left of the deck
January 2020: A temporary track winds around the burnt out bridge
May 2020: The temporary side track was washed away by flood waters and later rebuilt
March 2021: Gabion baskets are installed for the water spillway downhill from the bridge
April 2021: The concrete culverts are in place and the new road is being built above
May 2021: The bridge replacement was opened to traffic in early May
The final product: Guardrail lines the road over the new culverts
Previous
Next
Other areas
More info
For more information about please contact Council: